How the calculation works
Volume(ft³) = length(ft) × width(ft) × thickness(in) ÷ 12. Bags = ceiling(volume × (1 + allowance/100) ÷ mixed yield per bag). Cubic yards = cubic feet ÷ 27.
Measure the concrete space, not the excavation
Use the slab’s planned length and width and the thickness of concrete itself. A deeper excavation may also contain a base layer that should not be counted as concrete. If the slab has thickened edges, grade beams, steps, or other features, calculate their additional volumes separately with care to avoid overlaps. This form represents a single uniform rectangular layer.
Bag weight is not mixed volume
A dry bag’s weight does not directly tell you how much finished concrete it provides. The manufacturer’s mixed yield is the appropriate bridge from cubic feet to bags. The default yield uses QUIKRETE Concrete Mix No. 1101’s approximate eighty-pound bag value. Other mixes or package sizes may have different yields, so read the actual technical sheet and change the field before comparing counts.
Review the manufacturer’s stated yields
The product-specific yield table below provides several bag-size options from the same data sheet. Enter the corresponding cubic-foot yield rather than the number printed as the bag weight. Approximate yields remain estimates, and the tool does not change the manufacturer’s mixing instructions. Do not try to stretch coverage by changing the water quantity; use the product instructions for preparation and placement.
Keep extra volume tied to a real concern
The allowance is applied to geometric volume before dividing by bag yield. It is an adjustable planning estimate, not a universal concrete ordering rule. Uneven ground, form dimensions, and separate features should first be measured as well as practical. A large guessed allowance is a poor substitute for correcting a known dimensional error. Whole bags round up after that allowance is included.
Choose the supply method with the full job in mind
A bag count allows an arithmetic comparison with bulk cubic yards, but it does not determine a suitable mixing or placement plan. Check access, equipment, labor, product availability, and the supplier’s order increment separately. Reinforcement, joints, base preparation, curing, loading, and structural design require their own specifications. Consult the appropriate professionals and local requirements before constructing a slab where those decisions matter.
Worked example
The example slab uses a specified thickness and the published approximate yield of one identified bag size. Its measured cubic feet are increased by the example allowance before the bag count rounds up. The cubic-yard result remains available for discussing a different supply method with a concrete supplier.
Example inputs — Length: 12 ft; Width: 10 ft; Slab thickness: 4 in; Mixed yield per bag — 80 lb QUIKRETE 1101 estimate: 0.6 ft3; Extra material allowance (planning estimate): 10 %.
Calculated example
- Net volume (cu ft)
- 40
- Net volume (cu yd)
- 1.4815
- Order volume (cu yd, before supplier increment)
- 1.6296
- Whole bags to order
- 74
Concrete Mix No. 1101 bag yields
QUIKRETE lists approximate mixed yields of 0.30 cu ft for 40 lb, 0.375 for 50 lb, 0.45 for 60 lb, 0.60 for 80 lb, and 0.675 for 90 lb. Change the yield input to match your actual product and bag size.
Frequently asked questions
Can I enter a different concrete bag size?
Yes. Replace the yield field with the mixed volume stated for that specific product and size. Use the table only for the identified QUIKRETE mix, not as a guarantee for every bag of concrete.
Does this include reinforcement or footings?
No. It estimates one rectangular concrete layer. Additional features need separate measured volumes, and reinforcement or foundation design must come from the applicable plans and requirements.
Is the order volume ready-mix minimum included?
No. The cubic-yard result is an estimate before the supplier’s minimum delivery, selling increment, or job-specific ordering recommendation. Ask the ready-mix supplier how it wants the final quantity specified.
Sources and scope
- QUIKRETE — Concrete Mix No. 1101 technical data sheet — Approximate mixed yields: 40 lb = 0.30, 50 lb = 0.375, 60 lb = 0.45, 80 lb = 0.60, 90 lb = 0.675 cubic feet. These are product-specific. Accessed 2026-11-20.
- NIST Guide to the SI — Appendix B.8: Conversion Factors — Length, area, volume, and mass conversion definitions. Accessed 2026-11-20.